WV DNR: Hatchery Repairs are Finally Forthcoming
Charleston Gazette-Mail
21 January 2017
By John McCoy, Staff Writer
Sometime later this year, workers at West Virginia’s Apple Grove
Hatchery will be able to fill the facility’s 5-acre reservoir to
capacity. Tears in its fabric liner have prevented that from
happening for years. The liner repairs will allow the 17-year-old
facility to return to its normal fish-rearing capacity. The ponds
at Wirt County’s Apple Grove Hatchery will be easier to fill after
workers replace the facility’s ancient intake pump and make
repairs to the reservoir it fills. Things are looking up for West
Virginia’s warm-water fish hatcheries.
Division of Natural Resources officials have met with companies
expected to bid on work to fix major problems at the Apple Grove
and Palestine hatcheries. If bids are made and accepted, fish
production at both facilities should return to normal.
“The ball is rolling,” said Jim Hedrick, the DNR’s supervisor of
hatcheries. “I think we’re now on track to get things repaired
that have needed it for a long time.”Both hatcheries have had
trouble with the reservoirs that provide water to the facilities’
main buildings and to the ponds where fish are grown. At Apple
Grove, the reservoir can’t be filled because of rips in its
waterproof fabric liner. At Palestine, the reservoir can’t be
filled to capacity because its earthen retaining wall had sprung a
leak.
“As the pond liner at Apple Grove has continued to rip [deeper],
we have to lower the water level,” Hedrick explained. “If it gets
below a certain point, we won’t have [hydraulic] head to push
water into the hatchery building.
“At Palestine, we pump water [from the Little Kanawha River] to
the reservoir, but we can only pump a little because of its
limited capacity. It takes several [pump-and-drain] cycles to fill
a pond. If we could fill the reservoir to its capacity, we’d be
able to fill any pond just by opening a valve.”
Problems with Palestine’s 54-year-old intake pump aren’t helping
the situation. Hedrick said the pump can only be run at about half
its normal flow rate. “We have to be careful how we use that pump.
We don’t want it to go out on us or we would lose all our
[fish-rearing] capacity at Palestine,” he said. “Fortunately we’re
in the process of getting it replaced. Last week we had a pre-bid
meeting for purchase and installation of a new pump.” The
improvements at both facilities will give hatchery workers
considerably more room to grow fish, and much more freedom in the
way they do it.
“Over the past several years we’ve lost a considerable amount of
pond capacity,” Hedrick said. “With the ponds that are left, we’re
kind of putting all our eggs in one basket. If one of the ponds
fails, we won’t have a backup.” That, he added, has the potential
to cause shortages in the number of fish that the hatcheries could
provide. Unlike trout hatcheries, which produce only trout,
warm-water hatcheries produce several different species — most
notably, bass, walleye, muskellunge, catfish and bluegills. As
things stand, hatchery workers will have to juggle their
fish-rearing schedules to maintain the system’s anticipated
production.
Hedrick hopes to see work begin early this summer on the pond
liners at Apple Grove and the pump replacement at Palestine. The
work on Palestine’s reservoir, also a critical need, has not yet
been put out for bid.
“The guys at the hatchery have been cleaning up debris and trees
so the reservoir can be inspected by engineers,” Hedrick said. “We
want to make sure that when we get a contractor in here, there’s
no further work that will have to be done.”
He said a previous attempt to fix the reservoir failed because the
contractor “didn’t understand the scope of the work that needed to
be done. We don’t want that to happen again.”
The pond-liner work at Apple Grove is expected to cost about $5
million. The price tag will cover replacement of the 5-acre
reservoir’s liner plus the liners of 34 ponds scattered throughout
the facility. In all, 42 acres’ worth of new liners will be
installed. The original liners, installed when the hatchery was
built in the late 1990s, were supposed to last 15 to 20 years.
They didn’t. Hedrick said the new liners would be replaced in
phases.
“The most critical one is the reservoir’s,” he added. “Once we get
the liner in and the reservoir filled to capacity, we’ll be able
to put water in the other ponds as their liners are replaced and
they come back on line. As construction continues, we’ll gain
production capacity.”
Only then, Hedrick said, DNR officials will be able to breathe a
sigh of relief. “Right now we don’t have the security blanket
we’re used to having,” he said. “After the repairs we’ll have it
back.”
Reach John McCoy at johnmccoy@wvgazettemail.com, 304-348-1231 or
follow @GazMailOutdoors on Twitter.